2024 Updated Pricing
Dear Customer,
Due to increased prices on materials and diesel our concrete prices effective January 2024.
The new price per cubic metre will be as follows:
New Revised Price Old Price
C55 / 8000 psi at 28 days: $725.00 $690.00
C50 / 7250 psi at 28 days: $720.00 $685.00
C45 / 6500 psi at 28 days: $680.00 $650.00
C40 / 6000 psi at 28 days: $660.00 $625.00
C36 / 5250 psi at 28 days: $650.00 $620.00
C35 / 5000 psi at 28 days: $635.00 $605.00
C30 / 4500 psi at 28 days: $610.00 $580.00
C27 / 4000 psi at 28 days: $600.00 $565.00
C25 / 3750 psi at 28 days: $580.00 $550.00
C20 / 3000 psi at 28 days: $570.00 $540.00
C17 / 2500 psi at 28 days: $530.00 $505.00
C12 / 2000 psi at 28 days: $505.00 $480.00
C20 / *Kerb Mix 3000 psi at 28 days:
$600.00 $570.00
C25 / *Kerb Mix 3750 psi at 28 days:
$610.00 $580.00
*1 :3 Mortar
$670.00 $640.00
* 1 :4 Mortar
$610.00 $580.00
*1 :6 Mortar
$610.00 $580.00
C35 / *5000 Grout
$780.00 $740.00
C27 / *4000 RCC
$610.00 $580.00
The above prices are for mixes with a maximum 19mm aggregate. For mixes requiring aggregate with a maximum size of 1 Omm, there will be an extra
charge of $25.00 per cubic metre. These prices are subject to 17.5% Value Added Tax.
Dear Customer,
Due to the increase prices on materials our block prices effective 1st January 2024. The new block prices are as follows:
Charge Price Cash Price
300x200x400mm 12" $ 5.00
200x200x400mm 8” $ 3.25 $ 3.01
150x200x400mm 6" $ 2.60 $ 2.40
100x200x400mm 4" $ 2.25
Bond Beam 200x200x400mm 8"BB. $ 4.00
Half Block 200x200x200mm 1/2 8”s $2.00
Transportation rates are as follows:
1 Stage $ 100.00 per trip.
2nd Stage $ 110.00 per trip.
3rd Stage. $ 123.00 per trip.
4th Stage $ 138.00 per trip.
5th Stage $ 145.00 per trip.
6th Stage $ 150.00 per trip.
These prices are subject to 17.5% Value Added Tax.